Project Overview
Location: Ho Chi Minh city
Client: Consulat général de France à Ho Chi Minh-Ville
Scale: 35,000 sqm
Scope of work: Electrical system Installation
MEP Installation: 3,5 months
Project Information
Reecons was awarded to execute MEP works including power panel, power cables, cable tray and trunking, lighting fixtures and socket-outlets for services and workstations, HVAC system, and Fire fighting system for 4 commercial floors within 3,5 months.
With this tight given schedule, Reecons had to be well prepared and followed a strict schedule to combine closely with the Interior Design contractor to pass right behind handed-over areas.