PROJECT DETAIL

XP Power Vietnam Factory (Phase 2)

PROJECT OVERVIEW

DESCRIPTION

Project Overview

Location:               Binh Duong, Vietnam

Client:                    XP Power Vietnam

Scale:                     25,500 sqm

Scope of work:      Design & Build – Full MEP Package

MEP Installation:   8 months


 

Project Information

The Singaporean XP Power transformer manufacturing factory expanded its production capacity with an adjacent factory (Phase 2). Reecons was selected as the D&B contractor for the MEP package of the project, complying with LEED standards and strict safety requirements of the general contractor Boustead and the Investor’s representative, and ensuring the hand-over on time.

Among the scope of services: medium voltage system (22kV), 1600kVA station, switches (DS, Re-closer, RMU), back-up generator system (1600kVA) combined with EVN via ATS, electrical system from MSB cabinets to DB distribution cabinets, lighting power supply, HVAC (01 Chiller 450RT, 01 CT, 04 AHUs, 01 SEF, CHWPs, CWPs), compressed air system (2 Air compressors, 2 Air Dryers, 1 Air receiver Tank), Fire Protection System (Fire Alarm & Fire Fighting system), all monitored by BMS. All our systems operate stably on the basis of our design.


 

Features

OTHER PROJECTS

Hayat Kimya first production line in Vietnam
Sacombank Data Center
Private Luxury Villa
Sanofi First Factory in Vietnam
Satra Eximland Building
Jakob Factory Expansion
Onsemi Factory Renovation
Levi's Retail Stores
Mercedes-benz Tan Binh Showroom
French Consultate General Ho Chi Minh City

Trusted by international firms and partners 

Scroll to Top