PROJECT DETAIL

Vinagame Data Center

PROJECT OVERVIEW

Location: Ho Chi Minh City, Vietnam
Scale: 0 sqm.
Client: VNG Corporation
Scope of Services: Information technology & Digital services
Construction period: 10 months

DESCRIPTION

The first Data Center of VNG Corporation at 20 Cong Hoa, HCMC was designed and built to meet international standards of Data Center (TIA-942) – Tier 3+ – concurrently maintainable with 99.982% Vailability.

– Advanced network cabling system of Krone technology;
– The power system is backed up by 3 levels, with a capacity of 2000KVA, with 2 backup generators (1 machine / 1000KVA), connected to the LSSB main switchboard through an ATS automatic converter to ensure high availability on power supply;
– The UPS system includes batteries, JAP & PDU for an N+1 redundancy operated UPS system with 2-hour autonomy (at full load) blocks.
– The CRACs precision cooling system is cooled by the four CH-01-04 water chillers (2 x duty & 2 x standby ~ 260T/1 CH) to ensure that the servers operate continuously in high temperature conditions and the optimal
humidity;
– Specialized fire fighting system ensures early fire detection and automatic fire extinguishing with
extinguishing agents that are not harmful to equipment and workers;
– Security system and monitoring access and BMS system for the whole building and the construction site.

OTHER PROJECTS

Rebisco Biscuit Vietnam Factory
French Consultate General Ho Chi Minh City
Yau Hau Fook Restaurant
Aldo Shoes Retail Store
Boustead Ready Built Factories (Phase 1)
Nestle Binh An Factory
Satra Eximland Building
GREIF Flexible Vietnam Factory
Denis Canning Vietnam Factory
Backer Heating Vietnam Factory

Trusted by international firms and partners 

Scroll to Top